PMI Agile Certified Practitioner (PMI-ACP) — Question 10
Why should a project team reduce the work in progress?
Answer options
- A. It indicates poor project quality
- B. It represents team member's utilization
- C. It represents unrealized value
- D. It shows that the project is behind schedule
Correct answer: C
Explanation
Reducing work in progress helps to focus on completing tasks and delivering value more effectively, making option C the correct choice as it addresses unrealized value. Option A incorrectly associates work in progress with quality, while option B focuses on utilization rather than value, and option D misinterprets work in progress as an indication of scheduling issues.