PMI Agile Certified Practitioner (PMI-ACP) — Question 57

During a sprint review, the product owner identifies a required improvement for a feature's user interface (UI) delivered during the sprint.
What should the product owner do next?

Answer options

Correct answer: B

Explanation

The correct answer is B because prioritizing the new user interface improvement for the next sprint ensures that it is addressed promptly and efficiently. Option A delays action by placing it in the backlog without immediate focus. Option C incorrectly classifies the request as requirement creep, which is inappropriate in this context. Option D is not advisable as it increases the team's workload without proper planning.