PMI Agile Certified Practitioner (PMI-ACP) — Question 57
During a sprint review, the product owner identifies a required improvement for a feature's user interface (UI) delivered during the sprint.
What should the product owner do next?
Answer options
- A. Create a user story for this new improvement and put it in the product backlog for prioritization and validation by the customer
- B. Create a user story for this new improvement and prioritize it for the next sprint
- C. Document it as a requirement creep
- D. Ask the team to take on additional story points to improve the UI
Correct answer: B
Explanation
The correct answer is B because prioritizing the new user interface improvement for the next sprint ensures that it is addressed promptly and efficiently. Option A delays action by placing it in the backlog without immediate focus. Option C incorrectly classifies the request as requirement creep, which is inappropriate in this context. Option D is not advisable as it increases the team's workload without proper planning.