PMI Agile Certified Practitioner (PMI-ACP) — Question 56
During a sprint, the team encounters a technical problem that becomes an impediment to completing two stories.
What should the scrum master do?
Answer options
- A. Ask the lead developer to identify a solution, and then share the details with the team
- B. Ask a technical manager or architect to determine a solution to the problem
- C. Work with the product owner to add a spike to the next sprint to identify a solution
- D. Create a collaborative team environment so that the team can explore a solution together
Correct answer: D
Explanation
The correct answer is D because creating a collaborative environment allows the team to leverage diverse skills and perspectives to address the impediment effectively. Options A and B place the burden of problem-solving on a single individual rather than fostering team collaboration, while option C delays the resolution by pushing it to the next sprint instead of addressing it immediately.