PMI Agile Certified Practitioner (PMI-ACP) — Question 56

During a sprint, the team encounters a technical problem that becomes an impediment to completing two stories.
What should the scrum master do?

Answer options

Correct answer: D

Explanation

The correct answer is D because creating a collaborative environment allows the team to leverage diverse skills and perspectives to address the impediment effectively. Options A and B place the burden of problem-solving on a single individual rather than fostering team collaboration, while option C delays the resolution by pushing it to the next sprint instead of addressing it immediately.