PMI Agile Certified Practitioner (PMI-ACP) — Question 51

A product owner with experience in a predictive approach wants the team to develop very detailed schedules and cost estimates for the next 10 sprints.
What should the Scrum Master do?

Answer options

Correct answer: D

Explanation

The correct answer is D because agile methodologies do not prioritize detailed scheduling and budgeting as they are more flexible and adaptive to change. Options A, B, and C suggest creating or focusing on detailed plans, which contradicts the agile principle of responding to change over following a fixed plan.