PMI Agile Certified Practitioner (PMI-ACP) — Question 50

An agile team's client has been asked to expedite the delivery of the next release. By delivering one month early, the company can generate US$40,000 more than expected for the quarter.
What should the agile team do?

Answer options

Correct answer: B

Explanation

The correct answer is B because maintaining the original plan helps mitigate risks associated with rushing the project, which could affect quality. Options A and C introduce unnecessary changes that could jeopardize the project's integrity, while option D, although it suggests a solution, still risks compromising the project timeline and quality.