PMI Agile Certified Practitioner (PMI-ACP) — Question 332

A project team identifies a number of technical challenges with features in the next sprint.
What should they do?

Answer options

Correct answer: C

Explanation

The correct answer is C because determining who is best qualified to handle the challenges ensures that the right expertise is applied to resolve the technical issues effectively. Option A is not ideal as seeking direction may delay action, while option B prematurely reallocates features without attempting to solve the existing problems. Option D focuses on assigning tasks rather than identifying the right person to address the challenges.