PMI Agile Certified Practitioner (PMI-ACP) — Question 332
A project team identifies a number of technical challenges with features in the next sprint.
What should they do?
Answer options
- A. Request direction from the technical manager
- B. Encourage that product owner to reallocate the features to another sprint
- C. Determine who is best qualified to address the challenges
- D. Ask the product owner to assign the tasks to the most appropriately skilled resources
Correct answer: C
Explanation
The correct answer is C because determining who is best qualified to handle the challenges ensures that the right expertise is applied to resolve the technical issues effectively. Option A is not ideal as seeking direction may delay action, while option B prematurely reallocates features without attempting to solve the existing problems. Option D focuses on assigning tasks rather than identifying the right person to address the challenges.