PMI Agile Certified Practitioner (PMI-ACP) — Question 331

While reviewing the sprint burn down during a stand up, the scrum team identifies that they have fallen behind. Upon further discussion, they discover that some quality assurance (QA) team members were unable to use the new automation framework, which caused a bottleneck.
What should the scrum team do?

Answer options

Correct answer: D

Explanation

The correct answer is D because cross-training experienced QA members on the new automation framework allows the entire team to become more proficient and reduces bottlenecks. Options A and B do not directly address the immediate skill gap, while option C, though beneficial in the long run, does not resolve the current issue in a timely manner.