PMI Agile Certified Practitioner (PMI-ACP) — Question 323

A team member does not understand what the project risks are or the impact that they could have. How should an agile leader communicate risks in a way that the team will understand?

Answer options

Correct answer: D

Explanation

The correct answer is D because a risk burndown chart visually represents the reduction of risks, making it easier for team members to grasp their status and impact over time. The other options, while useful in their own right, do not directly address the need for clear understanding of risks in a visual and straightforward manner.