Early in a project, stakeholder analysis is performed; however, an organizational restructure redefines key roles.
What should the project team do?
Answer options
- A. Note the changes to the restructure and roles that affect team activities
- B. Use direct engagement and two-way conversation to update the stakeholder analysis for any new stakeholder requirements
- C. Email a copy of the project vision to those redefined for key roles and ask if they need to be involved in the project
- D. Obtain a copy of the redefined key roles to update the stakeholder analysis
Correct answer: B
Explanation
The correct answer is B because direct engagement fosters communication and ensures that any new stakeholder needs are accurately captured. Option A is insufficient as it only notes changes without updating analysis. Option C lacks proactive engagement and relies on passive communication, while option D does not involve actively revising the stakeholder analysis based on new insights.