PMI Agile Certified Practitioner (PMI-ACP) — Question 32

A product owner asks a newly formed scrum team how many story points will be completed in a sprint.
What should the scrum master do?

Answer options

Correct answer: D

Explanation

The correct answer is D because determining the sprint velocity requires actual data from completed sprints, which can only be gathered after running a few sprints. Options A, B, and C are incorrect as they rely on assumptions or external input rather than the team's own performance data.