PMI Agile Certified Practitioner (PMI-ACP) — Question 31

An agile coach is assigned to help a project team that was recently co-located close to a very popular business. Many team members visit this business during working hours which affects team performance.
What should the agile coach do to mitigate this issue?

Answer options

Correct answer: C

Explanation

The correct answer is C because involving the team allows for collaborative problem-solving and ownership of the solution. Options A and B focus on external management rather than directly addressing the team's needs, and D imposes penalties, which could further decrease morale and trust within the team.