PMI Agile Certified Practitioner (PMI-ACP) — Question 294

During a six-week iteration, an issue is identified by a team member. After analysis, the team member determines that it will take at least two weeks to resolve.

What should the team member do?

Answer options

Correct answer: A

Explanation

The correct action is to notify the product owner and begin resolution, as they need to be aware of potential delays and impacts on the project. Communicating in the stand up or retrospective may not provide timely updates needed for decision-making, and working on the next activity without addressing the issue could lead to further complications.