PMI Agile Certified Practitioner (PMI-ACP) — Question 293

An agile team has defined their definition of done (DoD) for a sprint. However, during the demo, the product owner is not sure if a user story can be marked as done.

Select the most appropriate sequence of activities that would need to be completed to meet a well-defined, mature definition of done (DoD).

Answer options

Correct answer: D

Explanation

Option D is the correct answer because it includes all necessary steps to ensure the user story meets the definition of done, such as unit testing, meeting acceptance criteria, and passing both functional and business testing. Other options either miss critical steps or do not follow the logical sequence required for a mature DoD, which could lead to incomplete work being marked as done.