A client has provided their requirements and deadline to the project team. The requirements are confusing, and the team is frustrated.

What should the team's servant leader do?

Answer options

Correct answer: C

Explanation

The correct answer is C because restating the requirements and reviewing them with the client helps clarify confusion and ensures everyone is on the same page. The other options, while potentially helpful, do not directly address the need for clarification of the requirements, which is critical at this stage.