PMI Agile Certified Practitioner (PMI-ACP) — Question 27
A product owner feels that the last sprint failed to sufficiently deliver what was valuable to their organization's overall project goals.
What should the scrum master mention at the next retrospective?
Answer options
- A. Solutions to project problems that were built into the last sprint
- B. Problems that arose
- C. Solutions that saved the organizations the most time and money
- D. Problems that were solved
Correct answer: B
Explanation
The correct answer is B because discussing the problems that occurred allows the team to understand what went wrong and how to improve in future sprints. Options A and C focus on solutions rather than identifying issues, which is crucial for retrospective discussions. Option D addresses solved problems, which may not provide insight into current challenges that need to be addressed.