PMI Agile Certified Practitioner (PMI-ACP) — Question 25

How can a scrum team obtain more feedback from a minimally responsive outside stakeholder?

Answer options

Correct answer: A

Explanation

Keeping sprints short allows for more frequent opportunities to present work and gather feedback, addressing the issue of the stakeholder’s minimal responsiveness. Inviting the stakeholder to daily stand-ups or scheduling more demos may not guarantee their active engagement. Asking for estimates can lead to pressure on the stakeholder without necessarily increasing their involvement in providing feedback.