PMI Agile Certified Practitioner (PMI-ACP) — Question 248

One of the senior stakeholders on a project did not want to be engaged on a daily basis. During the iteration, the team encounters complexities but are convinced these issues can be resolved in time for the demo.

What should the agile practitioner do?

Answer options

Correct answer: A

Explanation

The correct answer, A, emphasizes the importance of transparency in agile practices, ensuring that all stakeholders are kept informed about the project's challenges. Option B, while addressing risk, does not prioritize stakeholder communication. Option C disregards the need for transparency, and Option D places the decision on the product owner rather than taking proactive steps to engage stakeholders directly.