PMI Agile Certified Practitioner (PMI-ACP) — Question 241
A project team developer has been involved in a large corporate initiative that has negatively impacted team productivity on another project to which they have been assigned. How should the developer have handled this situation?
Answer options
- A. Worked as planned to meet the team's commitments and participated in other events as time permitted.
- B. Worked extensively on the corporate initiative in order to inform the team of that effort.
- C. Asked to be relieved of project tasks to maintain team velocity.
- D. Have not participated in any initiative that could take focus away from the team’s project and goals.
Correct answer: C
Explanation
The correct answer is C, as asking to be relieved of project tasks is a proactive way to protect the team's productivity. Options A and B may cause further distractions, while D is unrealistic as it does not allow for any involvement in important initiatives.