PMI Agile Certified Practitioner (PMI-ACP) — Question 234
A project has several features that will deliver immediate customer value. The product owner needs to determine which features to include in the upcoming iteration.
What should the product owner have the customer review and approve?
Answer options
- A. Work breakdown structure (WBS)
- B. Description of all features' functions and an estimate of their cost
- C. Priority list of desired features and functions
- D. Comprehensive schedule of immediate deliverables
Correct answer: C
Explanation
The correct answer is C because a priority list helps the product owner understand which features are most valuable to the customer, guiding them in making informed decisions about what to include in the iteration. Options A and D do not focus on customer preferences, while option B provides information but lacks prioritization, making it less effective for decision-making.