PMI Agile Certified Practitioner (PMI-ACP) — Question 232
A software project is being implemented by a small, colocated team. What should the project manager do to keep the team focused and engaged with the high level of requirements?
Answer options
- A. Arrange afternoon touchpoints where the team can discuss what they have done during the day.
- B. Request that the project sponsor is present during daily standups to increase commitment from the team.
- C. Send out daily activity tasks to each member of the team, mitigating the risk of tasks being forgotten.
- D. Make use of a kanban board so that the team will have a clear view of the work in progress (WIP) for the release.
Correct answer: D
Explanation
The correct answer is D, as a kanban board visually represents the workflow and helps the team track their progress on tasks, which enhances focus and engagement. Options A, B, and C may facilitate communication or accountability but do not provide the same level of clarity and ongoing visibility into work that a kanban board offers.