PMI Agile Certified Practitioner (PMI-ACP) — Question 231

After performing three sprints, the product owner and sponsor request an accurate schedule indicating when all releases will be delivered. What should the agile practitioner do?

Answer options

Correct answer: D

Explanation

The correct answer is D because providing a delivery range allows for flexibility and accommodates uncertainties in the development process while still giving the stakeholders a timeframe. Options A and B focus on creating a fixed schedule, which contradicts the adaptive nature of Agile, and option C relies on past projects that may not accurately reflect current conditions.