PMI Agile Certified Practitioner (PMI-ACP) — Question 229
During a retrospective, the team agrees that they have limited competence in using a newly introduced tool. What should the team do?
Answer options
- A. Explore options for increasing knowledge in the next iteration’s backlog.
- B. Experiment with the tool's usage by adding extra tasks in the current iteration.
- C. Propose alternative tools that the team is more competent using.
- D. Ask a tool expert to join the team and perform the relevant work.
Correct answer: A
Explanation
The correct answer is A because it focuses on improving the team's skills through planned learning opportunities in the next iteration. Options B and D may lead to ineffective use of the tool without proper knowledge, while C does not address the need to enhance competence with the new tool.