PMI Agile Certified Practitioner (PMI-ACP) — Question 228

A high-profile project team is struggling to meet planned velocity. During a retrospective, the team agreed that their lack of experience in the technology resulted in an excess of rework.

What should be done to resolve this challenge?

Answer options

Correct answer: D

Explanation

Implementing a spike allows the team to explore new ideas and techniques, which can help them gain the necessary experience with the technology and reduce rework. The other options either focus on changing iteration duration or testing, which do not directly address the root cause of the problem, that is, the team's lack of experience and the need for skill development.