PMI Agile Certified Practitioner (PMI-ACP) — Question 219
A project was delivered in a foreign country for a big customer, but there are a lot of complaints about the way the functionality was implemented. Now there is a new project to fix the defects of the first one.
What strategy should be used to deliver it successfully?
Answer options
- A. Talk with the old project manager to learn about the problems they encountered and the lessons learned.
- B. Suggest organizing a meeting in order to analyze the situation and work to find a strategy.
- C. Analyze all defects and change requests carefully to understand their root causes and act accordingly.
- D. Suggest an iterative approach including timely engagement of all key stakeholders and hold regular review meetings.
Correct answer: D
Explanation
The correct answer is D because an iterative approach allows for continuous feedback and adjustments from stakeholders, which is crucial for addressing defects effectively. While options A, B, and C focus on analysis and understanding the past, they do not emphasize the ongoing collaboration and adaptability needed for successful project delivery.