PMI Agile Certified Practitioner (PMI-ACP) — Question 218

The lead developer informed the team that they have learned of some possible integration challenges in creating customer dashboards using the architecture the team has chosen. What should an agile practitioner do?

Answer options

Correct answer: D

Explanation

The correct answer is D because it emphasizes recognizing the risk and taking proactive steps to investigate the integration challenges through a spike. Options A and B suggest actions that do not fully account for the risk management process, while option C ignores the new information regarding potential issues and maintains a status quo approach.