PMI Agile Certified Practitioner (PMI-ACP) — Question 196
A key resource is switching between projects to obtain more visibility and acclaim. However, project work has grown and become a burden.
What should the agile project leader do?
Answer options
- A. Add more resources to projects to ensure work sharing.
- B. Encourage the resource to undergo time management training.
- C. Ask management to ensure that the resource is available to only one project at a time.
- D. Allow the resource to continue switching between projects to deliver high customer value.
Correct answer: C
Explanation
The correct answer, C, is appropriate as it allows the resource to concentrate on a single project, improving efficiency and reducing their burden. Option A may not address the root cause of the issue, while B does not tackle the immediate workload problem. Option D could lead to burnout and lower quality work due to divided attention.