PMI Agile Certified Practitioner (PMI-ACP) — Question 193
Several new stakeholders are concerned about being asked to review a product demo before it is complete. How should the agile coach explain to the stakeholders the value of working this way?
Answer options
- A. The product owner may act as the stakeholders' proxy at the demo and that the stakeholders do not need to be directly involved with the team.
- B. The demo will show whether or not the team understands the level of effort required to complete the project.
- C. The stakeholders will learn whether or not the implementation has worked by getting immediate feedback so they can correct their assumptions for the next sprint.
- D. The stakeholders will be better positioned to evaluate whether or not the resources expended by the organization are worthwhile.
Correct answer: C
Explanation
Option C is correct because it highlights the importance of immediate feedback, allowing stakeholders to refine their expectations for future sprints. Options A and B do not emphasize feedback, while option D focuses on resource evaluation rather than the iterative learning process integral to agile methodology.