PMI Agile Certified Practitioner (PMI-ACP) — Question 193

Several new stakeholders are concerned about being asked to review a product demo before it is complete. How should the agile coach explain to the stakeholders the value of working this way?

Answer options

Correct answer: C

Explanation

Option C is correct because it highlights the importance of immediate feedback, allowing stakeholders to refine their expectations for future sprints. Options A and B do not emphasize feedback, while option D focuses on resource evaluation rather than the iterative learning process integral to agile methodology.