PMI Agile Certified Practitioner (PMI-ACP) — Question 189

What should a scrum master do when an agile team member is behind on their tasks?

Answer options

Correct answer: A

Explanation

The correct answer is A because involving the team in problem-solving fosters collaboration and may lead to effective solutions. Options B and C can disrupt team dynamics and may not address the root cause of the issue, while D does not provide immediate support to the team member.