PMI Agile Certified Practitioner (PMI-ACP) — Question 18

A scrum master is part of a project team using technologies overseen by the IT department. The IT director oversees several company initiatives and is unfamiliar with the details of each one.
As an active project stakeholder, to which meeting should the IT director be invited?

Answer options

Correct answer: C

Explanation

The IT director should be invited to the Sprint demo as it showcases the work completed during the sprint, allowing stakeholders to see progress and provide feedback. The Planning meeting is for setting up upcoming work, the Daily scrum is focused on team updates, and the Retrospective is about reflecting on the past sprint, which may not be as relevant for the IT director.