Throughout the project, an agile practitioner notices that one team member is becoming an emergent leader.
What should an agile practitioner do?
Answer options
- A. Present opportunities in order to be supportive and grow that team member's talents
- B. Encourage the team member to fit in more with the established team norms
- C. Bring this to management's attention so they don't disrupt the team
- D. Ask team member to respect defined roles on the project to avoid confusion with the team
Correct answer: A
Explanation
The correct answer is A because supporting the emergent leader can enhance the team's overall effectiveness and harness their skills for the benefit of the project. Options B and D focus on conformity and restrictions, which may stifle the team member's potential. Option C could undermine the team's dynamics and discourage natural leadership development.