PMI Agile Certified Practitioner (PMI-ACP) — Question 133

A team member has spent 5 days on a spike and the first set of experiments has not been successful. The issue is the development team member has determined a short-term rather than a long-term solution.
What should the project leader do?

Answer options

Correct answer: B

Explanation

The correct answer is B because re-estimating the spike and fostering collaboration encourages innovation and allows the team to explore different avenues for a long-term solution. Option A would shift responsibility without addressing the underlying issues, C halts progress and compromises the project's integrity, and D focuses on problems rather than solutions, which is not constructive in this scenario.