PMI Agile Certified Practitioner (PMI-ACP) — Question 118
An agile team has been given a complex project with a basic set of requirements which need further elaboration and review.
How should the team iteratively build out the backlog of requirements with the stakeholders?
Answer options
- A. Conduct a requirement gathering workshop
- B. Deliver the basic requirements iteratively
- C. Have the product owner fill out the requirements backlog
- D. Have the stakeholders fill out the backlog before starting the project
Correct answer: A
Explanation
The correct answer is A, as conducting a requirement gathering workshop allows for collaborative input and clarification from stakeholders, ensuring that the backlog is comprehensive. Options B and C do not involve stakeholder engagement in backlog development, and option D suggests completing the backlog before project initiation, which contradicts the iterative nature of agile practices.