What should a team do when they complete all sprint goals earlier than expected?

Answer options

Correct answer: C

Explanation

The correct answer is C because the product owner has the responsibility of prioritizing the backlog and selecting items that align with the project goals. Options A, B, and D either do not involve the product owner or suggest actions that are not in line with Scrum practices, which emphasize collaboration with the product owner for backlog decisions.