PMI Agile Certified Practitioner (PMI-ACP) — Question 109
What should a team do when they complete all sprint goals earlier than expected?
Answer options
- A. Begin working on an item in the backlog
- B. Ask the scrum master to select an item from the backlog on which to work
- C. Ask the product owner to select an item from the backlog on which to work
- D. Jointly decide with the scrum master on an item from the backlog on which to work
Correct answer: C
Explanation
The correct answer is C because the product owner has the responsibility of prioritizing the backlog and selecting items that align with the project goals. Options A, B, and D either do not involve the product owner or suggest actions that are not in line with Scrum practices, which emphasize collaboration with the product owner for backlog decisions.