PMI Agile Certified Practitioner (PMI-ACP) — Question 108

The customer needs assistance in determining the efficiency of a set of process activities within the solution.
What should the agile team do?

Answer options

Correct answer: B

Explanation

The correct answer is B, as reviewing the process value stream allows the team to pinpoint inefficiencies and implement improvements. Option A focuses on discussing efficiency rather than analyzing it, C prioritizes backlog items based on customer value instead of efficiency, and D addresses performance rather than the efficiency of process activities.