Program Management Professional (PgMP) — Question 65

A new program component provides an opportunity to enhance program outcomes. What does the program manager use to document and monitor the opportunity?

Answer options

Correct answer: A

Explanation

The correct choice is A, the Program risk register, as it is specifically designed to capture and track risks and opportunities that could impact the program. The other options, while related to program management, do not focus on documenting opportunities specifically. The Program scope management plan and the Program risk management plan are more about defining and managing the scope and overall risk strategies, respectively.