Program Management Professional (PgMP) — Question 58
A component project of a program is completed, and will provide the intended incremental benefits.
How should the program manager proceed with the component transition?
Answer options
- A. Update the program stakeholder engagement plan with stakeholders from the transition organization
- B. Define the component project's business value in the benefits management plan
- C. Update the program roadmap to reflect completion of a key end-point objective
- D. Initiate a program change request to close out the component project
Correct answer: A
Explanation
The correct answer is A because updating the stakeholder engagement plan ensures that all relevant stakeholders in the transition organization are informed and involved in the process. Options B and C do not directly address the transition process, and option D suggests closing the project rather than managing the transition effectively.