Program Management Professional (PgMP) — Question 54
Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?
Answer options
- A. Decompose the program work based upon available resources
- B. Decompose the program to the work package level
- C. Decompose the program to the architecture baseline level
- D. Decompose the program at a level sufficient to achieve control
Correct answer: D
Explanation
The correct answer is D because a program manager needs to ensure that the breakdown allows for adequate oversight and management of the program's progress. Options A, B, and C focus on specific aspects like resources, work packages, and architectural levels, which do not guarantee effective control over the program.