Program Management Professional (PgMP) — Question 5

A program completes all component projects and all identified benefits are being delivered. However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters.
To ensure the realization of long-term benefits, what should the program manager use?

Answer options

Correct answer: B

Explanation

The correct answer is B, the Benefits sustainment plan, as it focuses on maintaining and optimizing benefits over the long term. The other options, such as the Benefits register and Benefits management plan, are useful for tracking and managing benefits but do not specifically address the sustainability of those benefits over time.