Program Management Professional (PgMP) — Question 46
A program manager prepares the program for review to secure funding by senior management.
Which of the following must the program manager identify when creating the program charter?
Answer options
- A. Milestone dates, budget, and staff details that support it
- B. Assumptions incorporated into the benefits management plan
- C. Process within the organization that will be needed to deliver the product
- D. Key decision makers or stakeholders in the program and their expectations and interests
Correct answer: D
Explanation
The correct answer is D because identifying key decision makers and stakeholders is essential for understanding their expectations and interests, which is crucial for the program's success. Options A, B, and C focus on other aspects that are important but do not specifically address the need to recognize stakeholder involvement at the charter stage.