Program Management Professional (PgMP) — Question 45

You are the project manager for the JJY Project, which is similar to the HHG Project you managed last quarter. You would like to model the current project scope on the previous project to save time and effort. This is an example of what kind of scope definition?

Answer options

Correct answer: D

Explanation

The correct answer is D, as using a previous project as a template for the current project's scope is a classic example of a template-driven approach. Options A and C refer to estimation techniques rather than scope definition methods, while B relates to repository resources rather than a specific modeling technique.