Program Management Professional (PgMP) — Question 394

In preparation for the development and submission of the program master schedule to a client, the program manager meets with the component project manager and master program scheduler to discuss the work breakdown structure (WBS).
During the meeting, the master scheduler indicates that the master program schedule should include which of the following?

Answer options

Correct answer: D

Explanation

The correct answer is D because the master program schedule needs to cover all program activities, component activities, and any other relevant work to provide a comprehensive overview. Options A, B, and C are incorrect as they do not encompass the full scope of what should be included in the master schedule.