A program is developing a next-generation product line, and one component has been delivered. However, due to a change request, expectations for another component are unmet.
What activity should the program manager perform next?
Answer options
- A. Program delivery management
- B. Resource interdependency management
- C. Program performance monitoring and controlling
- D. Benefits sustainment and program transition
Correct answer: C
Explanation
The correct answer is C, as monitoring and controlling program performance allows the program manager to assess the impact of the change request and address any shortcomings. Options A and B focus on delivery and resource management, which are less relevant at this stage, while option D pertains to the program's conclusion rather than addressing current performance issues.