A project manager for a component, calls a program manager for advice. The project manager plans to schedule technical training for the project team on the critical skills needed for project delivery and asks the program manager which document to update.

Which document should the program manager advise the project manager to update for the required training?

Answer options

Correct answer: D

Explanation

The correct answer is D, Resource management plan, as it outlines the allocation and management of resources, including training for team members. The other options, such as the Stakeholder engagement plan, Training management plan, and Risk management plan, do not specifically address the scheduling and management of team training resources.