Program Management Professional (PgMP) — Question 373
A program manager has performed quantitative risk analyses for all identified program risks while creating a program risk management plan. The program manager and their team have also defined risk responses for each risk.
What should the program manager do next to ensure effective program risk management?
Answer options
- A. Review and update the risk register
- B. Monitor and control risks
- C. Communicate risks to stakeholders
- D. Implement risk responses
Correct answer: D
Explanation
The correct answer is D, as implementing risk responses is a crucial step in the risk management process to address identified risks. While reviewing the risk register, monitoring risks, and communicating to stakeholders are also important, they are not the immediate next steps after defining risk responses.