Program Management Professional (PgMP) — Question 367
A program manager has been directed to validate selected projects for alignment with organizational strategy. How should the program manager proceed?
Answer options
- A. Create and update the program mandate
- B. Revise and validate the program charter
- C. Update each component business case
- D. Review alignment with the organizational strategic plan
Correct answer: D
Explanation
The correct answer is D because reviewing alignment with the organizational strategic plan directly assesses whether the selected projects support overarching organizational goals. The other options involve documentation updates but do not specifically address the validation of alignment with strategy.