Program Management Professional (PgMP) — Question 346
You are the program manager for your organization. Management has asked you to create a document that will capture the stakeholders concerns, perceived threats, and specific objectives about the program and its projects. What document is management asking you to create in this instance?
Answer options
- A. Requirements document
- B. Project charter
- C. Business case
- D. Scope statement
Correct answer: C
Explanation
The correct answer is C, the Business case, as it is specifically designed to outline stakeholders' concerns, perceived threats, and objectives for a program. The other options, such as the Requirements document, Project charter, and Scope statement, focus more on specific project details rather than the broader business justification and stakeholder perspectives.