Program Management Professional (PgMP) — Question 309
During the delivery phase of a program, a program manager found opportunities to improve benefits by initiating multiple components within the current program structure.
What should the program manager do next?
Answer options
- A. Present the new opportunities to the program governance board for approval to initiate
- B. Assess the new and current components per the current program prioritization
- C. List the program's components by teams as they are needed to maximize benefits
- D. Determine the required resource allocation and interdependencies to initiate the components
Correct answer: A
Explanation
The correct answer is A because the program manager needs to seek approval from the program governance board before proceeding with any new opportunities. Options B, C, and D focus on assessing or organizing components rather than obtaining the necessary authorization, which is essential for initiating new efforts within a program.