Program Management Professional (PgMP) — Question 302
A program completes all component projects and all identified benefits are being delivered. However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters.
What can the program manager do to address the program sponsor's concern?
Answer options
- A. Send the benefits management plan to the program sponsor for review.
- B. Review the benefits sustainment plan with the component managers.
- C. Set up a meeting with the sponsor to review the benefits transition plan.
- D. Review the benefits register and check for the benefits requested.
Correct answer: B
Explanation
The correct answer is B because reviewing the benefits sustainment plan with the component managers ensures that there is a strategy in place to maintain benefits over time. Options A and C do not directly address the sustainability of benefits, while option D focuses on verification rather than long-term planning.