Program Management Professional (PgMP) — Question 302

A program completes all component projects and all identified benefits are being delivered. However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters.

What can the program manager do to address the program sponsor's concern?

Answer options

Correct answer: B

Explanation

The correct answer is B because reviewing the benefits sustainment plan with the component managers ensures that there is a strategy in place to maintain benefits over time. Options A and C do not directly address the sustainability of benefits, while option D focuses on verification rather than long-term planning.