Program Management Professional (PgMP) — Question 289
An organizational leader has been reviewing the newest marketing strategy plan and believes there is an opportunity to begin a new service line. A new program is approved with several active projects realigned under this program.
What should the program manager do next?
Answer options
- A. Establish the program roadmap
- B. Develop the program charter
- C. Establish the program committee
- D. Develop the program definition
Correct answer: B
Explanation
The correct answer is B, as developing the program charter is essential for defining the program's objectives, scope, and stakeholders. This step is crucial before moving on to establishing a roadmap, committee, or program definition, as the charter sets the foundation for all subsequent planning and execution.