Program Management Professional (PgMP) — Question 289

An organizational leader has been reviewing the newest marketing strategy plan and believes there is an opportunity to begin a new service line. A new program is approved with several active projects realigned under this program.

What should the program manager do next?

Answer options

Correct answer: B

Explanation

The correct answer is B, as developing the program charter is essential for defining the program's objectives, scope, and stakeholders. This step is crucial before moving on to establishing a roadmap, committee, or program definition, as the charter sets the foundation for all subsequent planning and execution.