Program Management Professional (PgMP) — Question 278

A program manager learns that their company's organizational strategy has changed. This change impacts one component project of a program, misaligning it with both the program objectives and the new organizational strategy. This component project, however, is already 90 percent complete.
What should the program manager do next?

Answer options

Correct answer: B

Explanation

The correct answer is B because assessing the impact of closure on other projects ensures informed decision-making and strategic alignment. Option A is premature, as it does not consider the effects on the overall program. Option C overlooks the misalignment and is not a strategic response. Option D, while important, does not address the immediate need to evaluate the implications of the closure on other components.